Civil Engineering - Railways.pdf

(3527 KB) Pobierz
61006680 UNPDF
U
.
'F
i
61006680.002.png
Rai I ways
9
61006680.003.png
Earthworks and drainage 2513
25.1 Earthworks and drainage
25.1.2.2 Rock cuttings
British Railways has indicated safe slopes for rock cuttings and
angles of repose for rock embankments in a chart reproduced as
Table 3 in BS 6031. If steep cuttings in rock are essential, then it
is necessary to apply engineering geology concepts to assess
joint sets in relation to the direction of slope. Rock anchors,
rock bolts and sprayed concrete may be used to assure stability
before considering the use of mass-retaining walls. Chalk and
certain other soft rocks are susceptible to weathering and frost
action and may be protected by vegetation cover.
The contours of the territory to be crossed by a railway are
obviouslv decisiveas to its average gradient but they are also the
background to fixing the maximum permissible gradient within
the limits of tractive and braking adhesion. The lower the
difference between average gradient and maximum gradient the
greater is the practicable train load and the lesser are the
deviations from constant-speed running. The minimum curva-
ture to be used also determines the differences between the line
speed limit and local speed restrictions. Long curves of small
radius on heavy gradients may involve derailment hazards for
very long and heavy trains, arising from braking or tractive
effort surges along the train. Both maximum gradient and
minimum curvature have a large effect on the earthworks cost of
constructing a railway and, because of this, the ideal of con-
stant-speed running is often subject to heavy qualification. This
is particularly the case in mountainous country.
Railway alignment needs to be planned to give a volume
balance between excavation in cuttings and tipping in embank-
ments, subject to the material excavated being suitable for
tipping to form embankments and subject to minimizing the
haul of the excavated soil. Recourse to borrow pits for embank-
ments and spoil hauls for cuttings should be minimized.
The route may also be affected by other considerations which
may be economic, environmental or technical. These would
become apparent in a full site investigation, where such matters
as previous mining activity, underground services, effect on
neighbouring structures, nature of the groundwater table and
watercourses would be taken into account. Guidance is avail-
able in relevant Codes of Practice, such as BS 6031 and BS 5930.
(See also Chapters 9, 1 I and 17.)
25.1.2.3 Soil cultings
Where the slopes are in noncohesive sands and gravels, the
angle of repose is the limiting gradient (with a maximum value
of I : I). Usually, the gradient is shallower than this due to the
presence of finer layers in the soil system or a silt or clay matrix
around the gravel. The non-cohesive soils tend to be self-
draining but erosion can occur when water springs part way up
the slope. At such locations a non-woven geotextile filter can be
placed and covered with uniform coarse stone (away from the
sun’s rays) which will hold the fabric in place.
Drainage measures should take the form of preventing water
reaching the slope and of removing it from the slope. Unlined
ditches behind the crest of the slope increase the hazard.
Drainage trenches, whether behind or below the crest, should be
designed to intercept water and have impermeable membranes
below them and on the downfill face to prevent water once
collected from re-entering the soil. Modem counterfort or
buttress drains differ greatly from the original open forms. Like
all drains they should be lined with a geotextile layer to prevent
erosion behind and fouling within them. The top I or 2m
should be composed of impermeable material, either compacted
clay fill or a system of stone and plastics membrane to prevent
surface water reaching deep into the ground, where it could
cause internal pore water pressure at likely slip surfaces.
In some cases, there is a mantle of more permeable silt or sand
overlying the older clay and, if possible, a lateral interceptor
drain should be placed about 20 m behind the crest to prevent
the fast seepage of water.
In addition to the above rotational slides, translational slides
can occur, usually as a shallow mass moving on a planar
surface. They can take the form of slab or block slides, wedge
failures, debris slides and flow slides. These possibilities are
assessed in the site investigation. Mires are formed as peat is laid
down in a specific sequence with variations in soil content,
dimensions of fibre (roots, trees, etc.) and extent of humifica-
tion. Peats reduce greatly in volume under the effects of loading
and drainage. In making cuttings in a peat system, quite
substantial waterflow can occur and a filter is advised to deal
with fine particles otherwise carried from the slope.
In all cases of cuttings, other engineering works at ground
level should be considered. Urban or industrial construction
involves roads which act as catchments to deliver water to local
drainage systems and also water services: if these are defective
and near the slope, water can flow to increase pore pressure and
precipitate a slip. Similarly, surcharging, especially if accompa-
nied by dynamic loads from construction plant or the placing of
storage containers, can seriously reduce the factor of safety.
Steep rock faces, chalk cliffs, and boulder-strewn hill slopes
may present rockfall or chalkfall problems which may need
special watchmen, signalling provisions, special fence, apron or
tunnel protection.
25.1.1 Site investigation
This will vary according to the extent of the problem. At the
outset, a preliminary study may give adequate information to
specify the route corridor from geological maps and memoirs,
topographical maps and aerial photographs. Earth satellite
imagery with interpretation of selective wavebands by special-
ists in remote sensing can indicate important features. Water
table conditions may vary throughout the year from those
obtaining at the time of exploration.
For more localized investigation, the type of equipment
(augers, percussion and rotary tools, penetration heads, loading
plates, pumps), instruments (piezometers, inclinometer tubes,
seismometers, resistivity meters, gravimeters, etc.) must be
chosen according to conditions. Relevant disturbed or undis-
turbed samples should be procured for testing. According to the
type of ground, the construction and the design philosophy
applied, it may be necessary to carry out full-scale site testing
with long-term monitoring of instruments.
25.1.2 General
In the past, railways have been maintained over poor ground,
with inadequate trackbed materials with a high input of labour
time and at slow or moderate train speeds. Although the
following concepts may be used in modifying old railways, the
basic approach is to obtain a minimum maintenance high-speed
railway accepting normal freight traffic on conventional
sleepers.
25.1.2.1 Cutting slopes
Slopes in natural ground may be constructed at safe angles
according to the properties of the soil.
25.1.2.4 Embankments
The nature of the natural soil to receive the embankment must
\
61006680.004.png
.
2514 Railways
be investigated. If it is too weak to receive the embankment
loading at the rate of placing likely to be used by the contractor,
failure could occur. A total stress analysis is applicable for this.
The conventional technique is to place berms as counterweights
at the position of heave. A modem alternative is the use of
reinforcing geotextiles or meshes (usually of plastics) to resist
tensile forces. The fabric is laid directly on the ground and
covered with a granular layer at least 200 mm thick; this acts as
a filter and permits construction plant to move easily over the
site without sinking into the underlying soft soil. Further fabric
or mesh is laid at higher levels, the number and spacing of layers
depending upon the engineering properties of the specialist type
of material chosen.
Drainage. The control of water in the trackbed is a major
factor in designing the construction layers in relation to the type
of subgrade soil as discussed above. Soils such as sands and
gravels which may be drained fairly easily donot present a great
problem unless there is an artesian head in this case, there can
be a slow upward migration of fine or medium sand under track
vibration combined with water flow, and a geotextile is neces-
sary to hold down this sand. Cohesive soils cannot be drained
easily and the installation of a channel or pipe will only reduce
the pore water pressure to invert level in its immediate vicinity.
It is not practical to attempt to remove water from clay in this
way as such a large number of drains would be required. If
water arrives through precipitation or by flow from adjacent
areas, then a relatively small amount is sufficient to produce
deleterious changes in pore pressure and so it is practical to
provide drains to intercept and remove this free water. Most of
the water in cohesive soil is held in capillary suction.
The relationship between the moisture content of cohesive
soil and the water table is complex, depending upon the over
consolidation ratio (OCR) of the soil. Weathering reduces the
OCR effect at the surface.
One object in designing the system of drains and track is to
produce a maintenance-free system or one needing minimal
attention. Channel drains are readily accessible for cleaning and
deal with rainwater, they can be laid at very slight gradients and
can deliver at catchpits to deeper pipe camers if necessary.
Many pipe drains act both as collectors and carriers, allowing
water to enter at open joints or through perforations. The
various forms of pipe are glazed earthenware, galvanized corru-
gated steel, pitch fibre and, now coming more into use because
of ease of handling, plain or perforated PVC pipe. Geotextiles
are of great use in static drainage conditions and most railways
report satisfactory results using commercially available filtering
non-woven fabric. For normal purposes, a fully heat-bonded
geotextile with a surface density in the range 100 to 200g/m2is
acceptable; needle-punched geotextiles should be of slightly
heavier grade. Fabrics placed in quasi-static conditions near the
track should be of heavier grade up to 350g/m*, or more if
needle-punched. Such a geotextile would be placed in the sixfoot
of a double track line after one track had been cleaned or
blanketed. This would prevent slurry from the dirty adjacent
track flowing across.
A modern standard design for a side drain is a trench lined
with geotextile with a perforated pipe drain running along its
base; above and around the pipe is placed uniform stone such as
ballast, with the top of the geotextile lapped over the stone
about 200 mm below the surface: more stone on the geotextile
protects it from disturbance and from the effect of the ultra-
violet rays of the sun. As perforated drains can release as well as
collect water, possibly at susceptible locations, it is often the
practice to place a polyethylene film to line the trench.
Slope angles. Embankments may be formed at angles varying
from ratios of 1 :1 horizontal to vertical for crushed rock and
gravels to 2.5: 1 or even shallower for clays and silts. The slope
angles depend both on the material and rainfall. For modem
railways, peat should not be used as fill material.
The surfaces of slopes should be protected from erosion. This
may occur naturally as vegetation is established, followed by a
protective topsoil. If surface erosion is a problem, various
systems are available, such as spraying with a seed mulch,
turving, placing filter fabrics held down by gravel layers or using
a honeycomb mesh to hold seeded compost in place.
Rockfalls. Vertical or sloping rock faces may erode or topple
to cause rocks of various sizes to fall towards the running line.
Although vegetation may help by bonding superficially, protec-
tion must involve coping with the energy of rockfall and
removing the debris regularly. If space is available, one or two
berms are constructed between the base of the slope and the
railway to collect scree. For some faces, a plastic geomesh is
adequate.
Reinforced earth. The dimensions of embankments and of
gravity-retaining structures can be reduced by the inclusion of
various strengthening meshes, fabrics, strips and rods of metal,
glass fibre or plastics. The tensile resistance of these elements is
applied to the adjacent granular soil to produce a composite
system permitting the construction of vertical faces in the fill.
These external faces are protected by facing elements usually of
concrete, resulting in a structure which is economic and which
can accommodate settlement. The various qualities of creep,
longevity of reinforcement, corrosion, etc. are still the subject of
study but many such structures exist throughout the world,
including railway environments. There are none so far beneath a
high-speed running line and, in this particular case, such systems
can be installed up to a horizontal distance of 5m from the
running line.
Trackbed designs. The thickness of subsleeper construction
(trackbed) is a function of number and size of axle loadings and
of the subgrade soil. Modern railways assess the subgrade soil in
one of two approaches: (I) the classification of the soil accord-
ing to its physical properties and taking account of the water
table; or (2) correlating some measured strength or modulus of
the subgrade with an empirical design chart. The thickness of
the trackbed may also depend upon its component layers to
protect against frost, water and particle movement. In very
frost-prone areas, such as Central Europe, the thickness of
ballast for frost protection exceeds that which might be required
for prevention of bearing capacity failure.
The thickness of ballast (all dimensions are below bottom of
sleeper) is a minimum of 200 mm to permit tamping machines to
operate. Although new ballast injection machines would permit
this to be reduced, a high-speed or high-axle-load railway would
require 300 to 500 mm thickness for minimum maintenance.
25.2 Ballast
Ballast, the material around and below the sleeper, is placed to
provide support and lateral resistance to the sleeper. It permits
adjustment of level and alignment as required and, if this is done
manually, the maximum size of particles should be about
50 mm. Ballast should be free-draining, mainly of single size, of
cubical shape but, above all, durable so that there is negligible
volume change under track loading. The wet attrition value
(WAV) gives the best correlation, with minimum maintenance
requirements over the long term and this is determined by the
test described in BS 812: 1951. clause 27, which specifies the
exact size and type of sample to be used. If particles of different
size from the 50 to 37.5 mm required in the test are used, then a
different WAV is obtained. The WAV should not exceed 4% for
61006680.005.png
Ballast 2515
good ballast and it is possible to obtain stone with a WAV down
to 1%. It is rare for synthetic stone, such as slag, to have
adequate wet attrition properties and they may generally be
grouped with most limestones as being unsuitable to be in
contact with the sleeper. Hardness is difficult to define in
relation to other tests but, if the ultrasonic pulse velocity of the
homogeneous mineral is 6000 m/s or greater, the stone will be
suitable. In severe climates, a freezing and thawing test may be
applicable.
The dimensions should conform by weight to the values
shown in Table 25.1; and the 1.18 mm limit effectively minimizes
the amount of dust present.
Table 25.1
nominal 20mm size between the ballast bed and the sleeper,
which is lifted to insert the stone. There is now a track-levelling
machine, electronically controlled, which evaluates cant and
level from an advancing inclinometer trolley and places the
exact quantity of stone by pneumatic injection to obtain proper
level. As stone more than 50 mm below the sleeper is not moved
and brought with its dirty matrix up to bottom sleeper level, as
with a tamper, the likelihood of pumping track is somewhat
lessened; the beneficial effect of high-quality small stone is not
reduced by mixing with existing worn stone and there is less
attrition of the base of the sleeper.
25.2.1 Track profile
Under traffic, rail level, as measured by accurate optical or
inclinometer-based machines, shows a profile which is repeated
even after many successive tamping and loading cycles. This is
related to the care with which the original trackbed layers were
installed. When the subgrade is prepared initially, and as
subsequent layers of blanket and ballast are placed and com-
pacted, it is necessary to provide extra sighting instruments on
compaction and grading plant so that there are no short
variations in level. This can be successfullydone by using a laser
system aimed at the surface a fixed distance ahead and which
causes the equipment to compensate for deviation from the
required level by moving its instrumented blade up or down.
The ends of the sleepers need to be boxed-in with shoulder
ballast to a minimum width of I50 mm for any tracks, 200 to
250 mm for running lines carrying moderate-speed, moderate-
axle-load traffic, 300mm minimum for welded track on the
straight and 350 mm for welded track on curves. Generally,
there is little advantage in extending shoulder ballasting beyond
300 to 350 mm. In the last decade or so, the practice of raising
the shoulder ballast in a slope from about top of sleeper level at
the rail to about top of rail level at the shoulder edge has become
common on European railways. This practice not only increases
the lateral stability of the track but provides a useful reserve of
boxing ballast which can be temporarily utilized to make good
the boxing ballast when the track is tamped. The angle of the
shoulder should be about 55'.
Square mesh
sieve
Yo topass
63
100
50
100-97
28
20-0
14
24
1.18
0.3-0
The stone should have a maximum flakiness index of 50%.
For elongation qualities, not more than 2% by weight of
particles should have a dimension exceeding 75 mm.
The effect of many tamping cycles is to break up ballast
particles; stone as hard as possible is required to accommodate
this. When a sleeper is tamped, a horizontal load - the major
principal stress - is applied to the ballast, causing it to deform
vertically and lift the sleeper. The minor principal stress is
vertical with the subsequent arrangement of stone particles in
the least favourable position to support track loading, even
though the rail level is now correct. The maximum rate of rail
settlement occurs after tamping, which reduces as the stone
packs down under traffic, with the major principal stress becom-
ing vertical. The trackbed becomes more stable under vertical
loading and the best relevelling procedure is the manual or
mechanical placing of measured quantities of small stones of
3307
- Id
3307
(Min. dimension)
(Min. dimension)
Pandrol rail.fastening
915
c
'\
\
1000-gauge
polythene sheet
Approved sand
I
where required
Pipe drain
Figure 25.1
rail (CWR) track (dimensions in millimetres)
Components and formation for continuous welded
61006680.001.png
Zgłoś jeśli naruszono regulamin